Client
Conseil Executif des Grands Projects de Beyrouth
Project Duration
24 Months
Description
Rehabilitation/renovation works in Beirut southern suburbs.
Type of Works
Rehabilitation and upgrading of roads and utilities in 250 main and secondary streets within Beirut southern suburbs. Works included the installation of sewage and water supply networks, in addition to sidewalk and asphalt works.
Excavation: 450,000m3
Asphalt: 26,000m3
Storm channels: 30,000m
Sewer Line: 26,000m
Water Supply Lines: 6,000m
Sidewalks: 50,000m2
Curbstone: 35,000m
Location
Beirut City Services Upgrading, Lebanon